Self-Storage Facility
PROJECT DETAILS:
MAS began erection of the 6 story storage facility in August of 2012. Working under a tight timeline, we were substantially complete with this project by December of 2012. Major obstacles for this project included an extremely tight site, working near the power lines and a fast schedule.
GENERAL CONTRACTOR: SSG Construction II, LLC
SQ. FOOTAGE: 143,000 SF
LOCATION: Somerville, MA
DURATION: 4 Months